The Challenges

BEST was selected as the lead exterior envelope contractor for this $350 million project performing a variety of work scopes, including furnishing &
installing Sarnafil PVC Roofing, Carlisle TPO Roofing, Stepstone Pedestal Pavers, Carlisle Barritech VP and CCW 705HT Air Barrier system, Sheet and Cementitious Waterproofing, American Hydrotech Hot Rubberized Asphalt Waterproofing, Sikalastic Traffic Coating at Pedestrian Walkway and Stadium Seats, Centria Intercept Series Architectural Metal Wall Panels, Centria Single Skin Wall Panels, Morin Standing Seam Metal Roofing, Alucobond ACM Wall Panels, Zahner Weatherized Corten Steel at Team Store – Lodge Seating – VIP East Entryway, Self-Fabricated Custom Prefinished Aluminum Coping, Plate, Flashing and Trim. BEST worked with lead architect Gensler and General Contractor PCL Construction Services to help deliver this historic project successfully and ahead of schedule.

Project Data

Building Use: Sports & Entertainment
Scope of Work: Sheet, Cementitious & Hot Rubberized Asphalt Waterproofing , Pedestal Pavers, Air Barriers, PVC & TPO Roofing, Metal & ACM Wall Panels, Standing Seam Metal Roofing
Location: Los Angeles, CA
Customer: PCL Construction Services, Inc.
Project Value: $7,198,386

Single Ply Roofing Crew

Left to Right: Bibiano Melendrez,Eduardo Ruiz Melendrez, Exter Azurin, Jose Rivera, Jesus Favela,Alan Rodrigues,Tobias Cumplido,Lavell Littlejohn,Jose Ramires, Efren Martinez,Jose Orta,Cecilio Valasco, and Carlos Cruz.

Architectural Sheet Metal Crew

Left to Right: Brian Robles, Lucas May, Danny Ledezma, Sal Rodriguez, Justin Doboiys, Ray Guiterrez, Jesse Guseman, Joseph Gayton, Joe Slapper, Sal Ramirez, Jeffrey Closure, Jesse Garcia, Marie Rios, Eddie Valadez (General Foreman Ruben Richards not shown).

Paver Crew

Left to Right: Jaime Remigio, Adrian Solis, Walter Vierra, Cresencio Regino,
Sergio Osorio, Nicolas Aviles, Isidro Hernandez