Mountain View High School Gym Modernization – Upper & Lower Decks
The Challenges
Mountain View High School was first established in 1971 and is part of the El Monte Union HS District with a student body population of approximately 1,500 students.
BEST was selected to furnish and install Sarnafil G410 60 mil PVC Single Ply roofing system in an area of 10,800 square feet on the Upper Deck and 19,000 square feet on the Lower Deck.
Project Data
Building Use: Educational
Scope of Work: Adhered Thermoplastic PVC Membrane Roofing
Location: El Monte, CA
Customer: Harik Construction, Inc.
Project Value: $341,574.00
Completion Date: October 2018
Scope of Work: Adhered Thermoplastic PVC Membrane Roofing
Location: El Monte, CA
Customer: Harik Construction, Inc.
Project Value: $341,574.00
Completion Date: October 2018