San Francisco International Airport Harvey Milk Terminal
The Challenges
First constructed in the early 1960s, Harvey Milk Terminal 1 is being redeveloped at an estimated cost of $2.4 billion to accommodate the millions of passengers traveling through SFO each year, while continuously providing world-class, environmentally friendly traveling experience.
BEST was selected to furnish and install approximately 460,000 square feet of Carlisle Membrane TPO roofing, which also included installing insulted concrete below the roofing membrane. Sheet Metal Flashing and Metal Roof Panels were also installed at designated areas.
Project Data
Building Use: Public Travel & Transportation
Scope of Work: Thermoplastic Polyolefin (TPO) Roofing
Location: San Francisco,CA
Customer: Austin Webcor JV
Project Value: $5,795,988.00
Completion Date: October 2019
Scope of Work: Thermoplastic Polyolefin (TPO) Roofing
Location: San Francisco,CA
Customer: Austin Webcor JV
Project Value: $5,795,988.00
Completion Date: October 2019
Call Us: (310) 328-6969
What roof is best for my needs?